Professional cleaning complete - Smart home configured - All systems commissioned
Bathroom fixtures and fittings selection meeting with Fatouros/Diakatou must be scheduled immediately. Critical path for May handover.
Interior paint colours to be selected by client during bathroom fixtures meeting. 4-day job after windows installation.
Exterior facade: painted finish OR PVC paneling - decision required. Both options compatible with LEED Platinum.
Dedicated EV charging station for Fatouros unit included in basement/parking scope. Target: end of March.
All smart home items ordered. Client configuration session required prior to move-in. Client must be present.
Certification submitted as complete package at end of construction. Energy audits at completion, 6mo, 12mo, 3yr, 5yr.